Week of June 2, 2025

The following summarizes the work planned at Eliot House during the week beginning Monday, June 2:

Dates: 06/02/25-06/06/25

PUBLIC WAY IMPACTS:

  • Liven up pedestrian walkway flashing light to notify the public of traffic pattern change on Memorial Drive (Monday 6/2); note: traffic pattern will not change until 6/9.

EXTERIOR SITE ACTIVITIES:

  • Brick washing on the south side of the southwest building from lift.
  • Washing archway leading into Eliot Hall courtyard.
  • Window removal at 7am Monday morning, June 2 for a Piano removal on the Level 2 library.

INTERIOR ACTIVITIES:

  • Removal of interior doors only.
  • Selective ceiling probes to facilitate historic element restoration.
  • Investigation and tracing of MEPs in Kirkland.

Gore Hall Impacts:

  • Electrical Shutdown in Gore Hall at 5am, Monday June 2 to install the breaker for the Pedestrian Walkway.

WORK HOURS:

  • Monday 5am-3pm
  • Tuesday-Friday 7am-3pm