The following summarizes the work planned at Eliot House during the week beginning Monday, June 9:

Dates: 06/09/25-06/13/25

PUBLIC WAY IMPACTS:

  • Shut down pedestrian crosswalk on Memorial drive. Pedestrians to be diverted to the river side of Memorial drive.
    • Cones and barriers will be set up to prevent pedestrians from walking past the new Memorial Drive crosswalk.
  • Installation of site fence around Eliot house renewal project.

EXTERIOR SITE ACTIVITIES:

  • Site fence installation around Eliot house
  • Archway and wrought iron removal.
  • Grubbing in courtyard.
  • Excavation for bridge support above tunnel.
  • Relocate existing utilities where future kitchen will sit.
  • Kitchen slab preparation on Dunster St.

INTERIOR ACTIVITIES:

  • Removal of interior doors.
  • Plumbing operations.
  • Steam operations.
  • Install plumbing risers in select stairwells.
  • Temp fire alarm installation.
  • Temp power installation.
  • Investigation and tracing of MEPs in Kirkland.
  • Selective demolition and shutdowns as needed for Kirkland.
    • Specific impacts noticeable to occupants’ building systems (electrical, domestic water, etc.) will be planned and communicated with Kirkland House building management.

WORK HOURS:

  • Monday-Friday 7am-5pm