The following summarizes the work planned on the Adams House Phase 3 renovation for the week of June 9. Please note that items in BOLD are expected to generate some noticeable noise.
Dates: 6/9/25-6/14/25
PUBLIC WAY IMPACTS:
- Continuous deliveries and dumpster swaps will occur throughout the week.
- A crane is scheduled for Wednesday June 11 to dismantle the Cupola Scaffolding. Plympton Street will be closed. Local traffic seeking access to the parking lots off Plympton Street will be able to access Plympton by driving the opposite way down the street from Mass Ave. A police detail will be on site to assist. Plympton Street will be re-opened at the end of day June 11.
EXTERIOR SITE ACTIVITIES:
- Masonry work on the exterior façade will continue for all buildings.
- Masonry & landscaping work will continue on the East Terrace outside of Westmorly Hall.
- Masonry Work will continue on the Lower Bow Site Walls
- Excavation, Concrete, & Masonry work will continue on the South Elevation outside of Westmorly Hall.
- Roofing installation is ongoing on the Library Commons roof.
- Window brickmold install and painting at Westmorly & Russell Hall.
- Conservatory Skylight Installation will continue
INTERIOR ACTIVITIES:
- Framing and drywall will continue within Westmorly & Russell Hall.
- Spray foam insulation will continue within Westmorly & Russell Hall.
- Floor prep & tile installation will continue within Westmorly.
- Millwork installation will continue within Westmorly.
- Hardwood flooring installation will continue within Westmorly & Russell Hall.
- Elevators will continue to be installed within Westmorly and Russell Hall.
SCHOOL OF PUBLIC HEALTH IMPACTS:
- Masonry work continues adjacent to 9 Bow and 22 Plympton Street.
- Excavation for the Waste and Recycling Storage Area will begin in the next week. This is directly adjacent to the 9 Bow Handicap Ramp. It will not impact access to the ramp
WORK HOURS:
- Monday-Friday 7:00am to 3:30pm.
- Saturday, June 14 – Site Open from 9:00am to 4:00pm
RANDOPH LAUNDRY ROOM:
INTERIOR ACTIVITIES:
- Demolition of the interior walls and ceilings will continue during week of 6/9
- Materials will be brought out the Courtyard towards Linden Street and picked up with our Lull to the Dumpster staged at Phase 3
- There will be impairments to the Fire Alarm and Sprinkler System made periodically as needed.
WORK HOURS:
- Monday-Friday 7:00am to 3:30pm
- Saturday, June 14- Site Open from 9:00am to 4:00pm