Day: June 16, 2025

Week of June 16, 2025

Week of: 6/16/25 – 6/20/25 Temporary Public Way Impacts: • The abatement subcontractor will be loading out CMU waste throughout the week. There will be temporary Palmer Street impacts (15-30 minutes) to remove the dumpsters. Exterior Site Activities: • No major exterior activities are scheduled for next week. Interior Activities: • Concrete chipping/demo activities ongoing…Continue Reading Week of June 16, 2025