Week of June 23, 2025

The following summarizes the work planned on the Adams House Phase 3 renovation for the week of June 23. Please note that items in BOLD are expected to generate some noticeable noise.

Dates: 6/23/25-6/28/25
 
PUBLIC WAY IMPACTS:

  • Continuous deliveries and dumpster swaps will occur throughout the week.
  • Plympton Street will be closed as needed to support sidewalk and paving repairs. Closure will also be needed to support lift access to the windows. Street Closure permits have been pulled. Access to upper Plympton will be available via MA Ave or the cut through from Linden Street

EXTERIOR SITE ACTIVITIES:

  • Masonry work on the exterior façade will continue for all buildings.
  • Masonry & landscaping work will continue on the East Terrace outside of Westmorly Hall.
  • Masonry Work will continue on the Lower Bow Site Walls
  • Excavation, Concrete, & Masonry work will continue on the South Elevation outside of Westmorly Hall.
  • Roofing installation will begin at the Servery Roof and Lower Connector Roof
  • Window brickmold install and painting at Westmorly & Russell Hall.
  • Conservatory Skylight Installation will continue
  • Plantings will continue along Bow Street. Evergreens are scheduled to be planted Tuesday June 24.
  • Sidewalk installation will continue
  • Irrigation installation will continue as planned

INTERIOR ACTIVITIES:

  • Framing and drywall will continue within Westmorly & Russell Hall.
  • Floor prep & tile installation will continue within Westmorly and Russell Hall
  • Millwork installation will continue within Westmorly and Russell Hall
  • Hardwood flooring installation will begin in the Dining Hall and Lower Common Room
  • Elevators will continue to be installed at the Conservatory
  • Equipment installation will continue in the Kitchen Areas
  • Fire Alarm Testing may begin towards the end of this week. Alarms may be audible during this time.

SCHOOL OF PUBLIC HEALTH IMPACTS:

  • Masonry work continues adjacent to 9 Bow and 22 Plympton Street.
  • Construction of the Waste and Recycling Area will continue. This is adjacent to the 9 Bow Handicap Ramp but wont affect access
  • We will continue to prep area adjacent to 22 Plympton. We will maintain as much of the parking spaces as possible.
  • Installation of the Library Chimney Cap will begin from a lift on Plympton Street. This will be visible from 22 Plympton Street but wont have impact to access to their building

WORK HOURS:

  • Monday-Friday 7:00am to 6:00pm.
  • Saturday 6/28/2025 – Site Open from 9:00am to 4:00pm

RANDOPH LAUNDRY ROOM:
INTERIOR ACTIVITIES:

  • Materials will be brought out the Courtyard towards Linden Street and picked up with our Lull to the Dumpster staged at Phase 3
  • There will be impairments to the Fire Alarm and Sprinkler System made periodically as needed.
  • Framing will continue within the Laundry Room
  • Mechanical and Electrical work will continue as planned

WORK HOURS:

  • Monday-Friday 7:00am to 3:30pm.