The following summarizes the work planned at Eliot House during the week beginning Monday, June 23:
Dates: 06/23/25-06/29/25
PUBLIC WAY IMPACTS:
- Shut down pedestrian crosswalk on Memorial drive. Pedestrians to be diverted to river side of Memorial drive.
- Cones and barriers are set up to prevent pedestrians from walking past the new Memorial Drive crosswalk.
- Site fence around Eliot house renewal project
EXTERIOR SITE ACTIVITIES:
- Install soil protection within courtyard
- Excavation for bridge support above tunnel
- Archway stone removal by masons
- Scaffold/ Trash chute install in Eliot Courtyard
- Land Transformer pad for Temp Power
- Erosion and sedimentation control plan
- Relocate existing utilities where future kitchen will sit
- Wilscott Bathroom Trailer delivery and install 6/26-6/27
INTERIOR ACTIVITIES:
- Salvage and protection of surfaces inside building historic spaces
- Plumbing Cut/Cap and Temp Riser install
- Temp fire alarm install in Eliot house
- Temp power install in Eliot house
- Swap Smoke detectors for heat detectors for Kirkland Kitchen Alterations
- Disable Ansul system for exhaust hood demo
- Relocate loading dock fire alarm panel in connector building
- Selective demo and shut downs as needed for Kirkland – all shut downs impacting Kirkland planned and communicated in advance
Weekend Activities:
- 6/21:
- Masons dismantle archway
- Temp Plumbing riser install
- Soil protection in quad and backfill duct bank on Dunster Street
- Remove Kirkland Kitchen windows
- Pipefitters continue re-routing at dumbwaiter
- Electricians make safe in Kirkland Kitchen
- 6/28:
- Soil protection in Eliot courtyard
- Scaffold install in Eliot courtyard
- Bridge install in Eliot courtyard
- Kirkland Kitchen Project interior demo as needed
WORK HOURS:
- Monday- Friday 7am-4pm
- Saturday 9am-5pm