Week of June 30, 2025

The following summarizes the work planned at Eliot House during the week beginning Monday, June 30:

Dates: 06/30/25-07/06/25

PUBLIC WAY IMPACTS:

  • Shut down pedestrian crosswalk on Memorial drive. Pedestrians to be diverted to river side of Memorial drive.
    • Cones and barriers are set up to prevent pedestrians from walking past the new Memorial Drive crosswalk.
  • Site fence around Eliot house renewal project

EXTERIOR SITE ACTIVITIES:

  • Asphalt courtyard Monday & Tuesday
  • Excavation for bridge support above tunnel
  • Archway stone removal by masons
  • Scaffold/ Trash chute install in Eliot Courtyard
  • Temp Power conduit install in Mac Quad
  • Trenching and pipe install for trailer plumbing in Mac Quad
  • Erosion and sedimentation control
  • Fence install around trailers in Mac Quad
  • Framing on kitchen-to-go slab

INTERIOR ACTIVITIES:

  • Salvage and protection of surfaces inside building historic spaces
  • Plumbing Cut/Cap/drain and Temp Riser install and liven up
  • Temp fire alarm install in Eliot house
  • Temp power install in Eliot house
  • Selective demo and shut downs as needed for Kirkland – all shut downs impacting Kirkland planned and communicated in advance
  • Concrete place ejector pit walls and house keeping pads of Kirkland Kitchen
  • Steam room fitout in Kirkland kitchen

Weekend Activities:

  • 6/28:
    • Soil protection and erosion control on Memorial Drive and Eliot quad
    • Archway removal
    • Kirkland Kitchen Project interior demo as needed
    • State electrical fitout interior
  • 7/5:
    • No work on 4th of July Weekend

WORK HOURS:

  • Monday- Thursday 7am-4pm
  • Friday Off for 4th of July
  • Saturday 9am-5pm