The following summarizes the work planned at Eliot House during the week beginning Monday, June 30:
Dates: 06/30/25-07/06/25
PUBLIC WAY IMPACTS:
- Shut down pedestrian crosswalk on Memorial drive. Pedestrians to be diverted to river side of Memorial drive.
- Cones and barriers are set up to prevent pedestrians from walking past the new Memorial Drive crosswalk.
- Site fence around Eliot house renewal project
EXTERIOR SITE ACTIVITIES:
- Asphalt courtyard Monday & Tuesday
- Excavation for bridge support above tunnel
- Archway stone removal by masons
- Scaffold/ Trash chute install in Eliot Courtyard
- Temp Power conduit install in Mac Quad
- Trenching and pipe install for trailer plumbing in Mac Quad
- Erosion and sedimentation control
- Fence install around trailers in Mac Quad
- Framing on kitchen-to-go slab
INTERIOR ACTIVITIES:
- Salvage and protection of surfaces inside building historic spaces
- Plumbing Cut/Cap/drain and Temp Riser install and liven up
- Temp fire alarm install in Eliot house
- Temp power install in Eliot house
- Selective demo and shut downs as needed for Kirkland – all shut downs impacting Kirkland planned and communicated in advance
- Concrete place ejector pit walls and house keeping pads of Kirkland Kitchen
- Steam room fitout in Kirkland kitchen
Weekend Activities:
- 6/28:
- Soil protection and erosion control on Memorial Drive and Eliot quad
- Archway removal
- Kirkland Kitchen Project interior demo as needed
- State electrical fitout interior
- 7/5:
- No work on 4th of July Weekend
WORK HOURS:
- Monday- Thursday 7am-4pm
- Friday Off for 4th of July
- Saturday 9am-5pm