Day: June 30, 2025

Week of June 30, 2025

The following summarizes the work planned on the Adams House Phase 3 renovation for the week of June 30. Please note that items in BOLD are expected to generate some noticeable noise. Dates: 6/30/25-7/6/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: INTERIOR ACTIVITIES: SCHOOL OF PUBLIC HEALTH IMPACTS: WORK HOURS: RANDOPH LAUNDRY ROOM:INTERIOR ACTIVITIES: WORK HOURS:…Continue Reading Week of June 30, 2025