The following summarizes the work planned at Eliot House during the week beginning Monday, July 7:
Dates: 07/07/25-07/13/25
PUBLIC WAY IMPACTS:
- Shut down pedestrian crosswalk on Memorial Drive. Pedestrians to be diverted to river side of Memorial Drive.
- Cones and barriers are set up to prevent pedestrians from walking past the new Memorial Drive crosswalk.
- Site fence around Eliot house renewal project
EXTERIOR SITE ACTIVITIES:
- Archway/Pier removal by masons
- Scaffold/ Trash chute install in Eliot Courtyard and JFK side of Eliot House
- Dumpster deliveries within Eliot Courtyard
- Temp Trailer Power install in Mac Quad
- Temp lighting install along site fence and trailer fence in Mac Quad
- Heat trace/insulate plumbing to trailers in Mac Quad
- Sanitary drainage install in Mac Quad
- Framing for temporary Kirkland Kitchen
- Cut dumbwaiter opening for Kirkland Kitchen
- Loading dock concrete pad excavation, prep, and pour
INTERIOR ACTIVITIES:
- Salvage and protection of surfaces inside building historic spaces
- Demo; loadout via trash chutes in Eliot Courtyard
- Abatement
- Plumbing/Mechanical Cut/Cap/drain
- Temp fire alarm install in Eliot house
- Temp power install in Eliot house
- Selective demo and shut downs as needed for Kirkland – all shut downs impacting Kirkland planned and communicated in advance
- Dumbwaiter CMU Shaft for Kirkland Kitchen
- Steam room fit out in Kirkland Kitchen
Weekend Activities:
- 7/12:
- Archway and Brick removal inside Eliot courtyard
WORK HOURS:
- Monday- Friday 7am-11pm (2 Shifts)
- Saturday 9am-5pm