The following summarizes the work planned at Eliot House during the week beginning Monday, July 7:​​​​​

Dates: 07/07/25-07/13/25

PUBLIC WAY IMPACTS:

  • Shut down pedestrian crosswalk on Memorial Drive. Pedestrians to be diverted to river side of Memorial Drive.
    • Cones and barriers are set up to prevent pedestrians from walking past the new Memorial Drive crosswalk.
  • Site fence around Eliot house renewal project

EXTERIOR SITE ACTIVITIES:

  • Archway/Pier removal by masons
  • Scaffold/ Trash chute install in Eliot Courtyard and JFK side of Eliot House
  • Dumpster deliveries within Eliot Courtyard
  • Temp Trailer Power install in Mac Quad
  • Temp lighting install along site fence and trailer fence in Mac Quad
  • Heat trace/insulate plumbing to trailers in Mac Quad
  • Sanitary drainage install in Mac Quad
  • Framing for temporary Kirkland Kitchen
  • Cut dumbwaiter opening for Kirkland Kitchen
  • Loading dock concrete pad excavation, prep, and pour

INTERIOR ACTIVITIES:

  • Salvage and protection of surfaces inside building historic spaces
  • Demo; loadout via trash chutes in Eliot Courtyard
  • Abatement
  • Plumbing/Mechanical Cut/Cap/drain
  • Temp fire alarm install in Eliot house
  • Temp power install in Eliot house
  • Selective demo and shut downs as needed for Kirkland – all shut downs impacting Kirkland planned and communicated in advance
  • Dumbwaiter CMU Shaft for Kirkland Kitchen
  • Steam room fit out in Kirkland Kitchen

Weekend Activities:

  • 7/12:
    • Archway and Brick removal inside Eliot courtyard

WORK HOURS:

  • Monday- Friday 7am-11pm (2 Shifts)