The following summarizes the work planned at Eliot House during the week beginning Monday, July 21:
Dates: 07/21/25-07/27/25
PUBLIC WAY IMPACTS:
- Complete sewer tie-in off the Mac Quad.
EXTERIOR SITE ACTIVITIES:
- Archway/pier removal by masons ongoing.
- Scaffold install on the Southwest building.
- Begin demo /abatement of Southwest building roof.
- Removal of exterior doors and lights set to be refurbished.
- Continuous daily dumpster swaps during first shift.
- Begin roofing Kirkland kitchen.
INTERIOR ACTIVITIES:
- Salvage and protection of surfaces inside building historic spaces.
- Demo and abatement using trash chutes.
- Plumbing/mechanical cut/cap/drain.
- Temp power install in Eliot House.
- Selective demo and shutdowns as needed for Kirkland House – all shutdowns impacting Kirkland are planned and communicated in advance.
- Steam room fit out in Kirkland kitchen.
Weekend Activities:
- 7/19:
- Archway and brick removal inside Eliot House courtyard
- Modular kitchen assembly
- Air and vapor barrier (AVB) at Kirkland kitchen
- Mechanical, electrical, and plumbing (MEP) trades working in new steam room.
- 7/20
- Modular kitchen assembly.
WORK HOURS:
- Monday- Friday 7am-11pm (2 Shifts)
- Saturday 9am-5pm