Day: August 13, 2025

Week of August 11, 2025

General Project Information Exterior Plaza Work Scheduled for week of 8/11/2025 Expected Impacts – high noise levels from chipping, cutting, and grinding will be most noticeable in areas west of the building footprint. Interior Work Scheduled for week of 8/11/2025 Expected Impacts – high noise level from cutting, chipping and grinding….Continue Reading Week of August 11, 2025

Week of August 4, 2025

General Project Information Exterior Plaza Work Scheduled for week of 8/4/2025 Expected Impacts – high noise level from chipping, cutting and grinding will be most noticeable in areas west of the building footprint. Interior Work Scheduled for week of 8/4/2025 Expected Impacts – high noise level from cutting, chipping and grinding….Continue Reading Week of August 4, 2025