The following summarizes the work planned at Eliot House during the week beginning Monday, August 25, 2025:​​​​​

Dates: 08/25/25-08/31/25
 
PUBLIC WAY IMPACTS:

  • None

EXTERIOR SITE ACTIVITIES:

  • Demo of masonry loading bay areas.
  • Exterior washing of masonry façade.
  • Scaffold installation on the North building.
  • Demo / abatement of Southwest building roof.
  • Continuous daily dumpster swaps during first shift.
  • Removal of existing utilities at Dunster St. Circle to prep for connector demolition.

INTERIOR ACTIVITIES:

  • Salvage and protection of surfaces inside building’s historic spaces.
  • Regulated materials removal.
  • Demolition using lulls / trash chutes.
  • Plumbing/mechanical cut/cap/drain at connector.
  • Selective demo and shutdowns as needed for Kirkland – all shutdowns impacting Kirkland are planned and communicated in advance.

Weekend Activities:

  • 08/23/25
    • Demo / abatement of southwest building roof (JFK Street side.)
    • Demo / abatement Eliot House.
    • MEP trades working Kirkland basement.

WORK HOURS:

  • Monday- Friday 7am-11pm (Two Shifts)