The following summarizes the work planned at Eliot House during the week beginning Monday, August 25, 2025:
Dates: 08/25/25-08/31/25
PUBLIC WAY IMPACTS:
- None
EXTERIOR SITE ACTIVITIES:
- Demo of masonry loading bay areas.
- Exterior washing of masonry façade.
- Scaffold installation on the North building.
- Demo / abatement of Southwest building roof.
- Continuous daily dumpster swaps during first shift.
- Removal of existing utilities at Dunster St. Circle to prep for connector demolition.
INTERIOR ACTIVITIES:
- Salvage and protection of surfaces inside building’s historic spaces.
- Regulated materials removal.
- Demolition using lulls / trash chutes.
- Plumbing/mechanical cut/cap/drain at connector.
- Selective demo and shutdowns as needed for Kirkland – all shutdowns impacting Kirkland are planned and communicated in advance.
Weekend Activities:
- 08/23/25
- Demo / abatement of southwest building roof (JFK Street side.)
- Demo / abatement Eliot House.
- MEP trades working Kirkland basement.
WORK HOURS:
- Monday- Friday 7am-11pm (Two Shifts)
- Saturday 9am-5pm