GENERAL OCCUPANT INFORMATION
- Phase 1 – high noise level work is scheduled to continue through third week of September.
PLAZA WORK: Week of 8/25/2025
- Concrete demolition in west areaway continues.
- Concrete repairs in the north areaways continue.
- Removal of flood testing damming in North/West/South Areas of plaza. Followed by light grinding of Kemper for alkalinity topcoat.
- Relocation of tools and materials out of planter D for grade beam installation on top of plywood protection.
- Re-working existing tent structure for upcoming Phase 1A demo and abatement.
- Installation of protection over entire Kemper surface as needed.
IMPACTS- High noise level from chipping, cutting and grinding will be most noticeable in areas N and W of building footprint.
INTERIOR WORK: Week of 8/25/2025
- Concrete demolition in mechanical room.
IMPACTS- high noise level from cutting, chipping and grinding