Week of August 25, 2025

GENERAL OCCUPANT INFORMATION

  • Phase 1 – high noise level work is scheduled to continue through third week of September.

PLAZA WORK: Week of 8/25/2025

  • Concrete demolition in west areaway continues.
  • Concrete repairs in the north areaways continue.
  • Removal of flood testing damming in North/West/South Areas of plaza. Followed by light grinding of Kemper for alkalinity topcoat.
  • Relocation of tools and materials out of planter D for grade beam installation on top of plywood protection.
  • Re-working existing tent structure for upcoming Phase 1A demo and abatement.
  • Installation of protection over entire Kemper surface as needed.

IMPACTS- High noise level from chipping, cutting and grinding will be most noticeable in areas N and W of building footprint.

INTERIOR WORK: Week of 8/25/2025

  • Concrete demolition in mechanical room.

IMPACTS- high noise level from cutting, chipping and grinding