Week of September 2, 2025

GENERAL BUILDING OCCUPANT INFORMATION

  • The plaza renovation project is targeting an end of May 2026 completion date.
  • Phase 1 high noise level work is scheduled to continue through October.

PLAZA WORK: Week of 9/2/2025

  • Concrete demolition in west areaway continues.
  • Concrete repairs in the north areaways continue.
  • Concrete placement in planter for structures on Thursday.
  • Tent dismantling at north side as soon as Saturday.
  • Trucking deliveries throughout the week.
  • Installation of protection over entire Kemper surface as needed.

IMPACTS- high noise level from chipping, cutting and grinding will be most noticeable in areas N and W of building footprint.

INTERIOR WORK: Week of 9/2/2025

  • Concrete demolition in mechanical room.
  • Interior relocations for repairs in mechanical room

IMPACTS- high noise level from cutting, chipping and grinding.