GENERAL BUILDING OCCUPANT INFORMATION
- The plaza renovation project is targeting an end of May 2026 completion date.
- Phase 1 high noise level work is scheduled to continue through October.
PLAZA WORK: Week of 9/2/2025
- Concrete demolition in west areaway continues.
- Concrete repairs in the north areaways continue.
- Concrete placement in planter for structures on Thursday.
- Tent dismantling at north side as soon as Saturday.
- Trucking deliveries throughout the week.
- Installation of protection over entire Kemper surface as needed.
IMPACTS- high noise level from chipping, cutting and grinding will be most noticeable in areas N and W of building footprint.
INTERIOR WORK: Week of 9/2/2025
- Concrete demolition in mechanical room.
- Interior relocations for repairs in mechanical room
IMPACTS- high noise level from cutting, chipping and grinding.