175 North Harvard Street The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART):…Continue Reading Week of September 8, 2025
Week of September 8, 2025
GENERAL OCCUPANT INFORMATION IMPACTS: Phase 1 high noise level work is scheduled to continue through October. PLAZA WORK: Week of 9/8/2025 INTERIOR WORK: Week of 9/8/2025…Continue Reading Week of September 8, 2025
Week of September 8, 2025
The following summarizes the work planned at 12 Palmer St for the week of September 8. Please note that items in BOLD are expected to generate some noticeable impacts. Week Of: 9/8/25 – 9/12/25Temporary Public Way Impacts:• Road closure tentatively scheduled for Wednesday 9/10/25 for a crane pick.• There will be short-term deliveries on Palmer Street.Exterior Site…Continue Reading Week of September 8, 2025