The following summarizes the work planned at Eliot House during the week beginning Monday, September 15, 2025:
Dates: 09/15/25 – 09/20/25
PUBLIC WAY IMPACTS:
- Dumpster Swaps (5x a day) from Dunster Circle for the connector building demolition beginning Thursday 9/18/25. A laborer and HUPD will be staged in the crosswalk in front of Kirkland to help with pedestrian traffic.
EXTERIOR SITE ACTIVITIES:
- Demo of masonry banding around building.
- Exterior washing of masonry façade.
- Scaffold installation on the North building and chimneys in the SW.
- Demo / abatement of north building roof.
- Continuous daily dumpster swaps during first shift.
- Connector Demolition at Dunster St.
INTERIOR ACTIVITIES:
- Saw cutting basement labs.
- Drilling piles in basement.
- Demolition using lulls / trash chutes.
Weekend Activities:
- 09/13/25
- Demo / abatement of southwest building roof.
- Demo / abatement Eliot House.
- Setting Control L5.
WORK HOURS:
- Monday- Friday 7am-11pm (Two Shifts).
- Saturday 9am-5pm.