Week of September 15, 2025

GENERAL OCCUPANT INFORMATION

  1. The plaza renovation project is targeting an end of May 2026 completion date.
  2. Phase 1 high noise level work is scheduled to continue through October. Refer to TWLA schedule for further detail.

PLAZA WORK: Week of 9/15/2025 

  1. Concrete repairs in west areaway continues.
  2. Concrete repairs in the mechanical room/basement.
  3. Scaffolding demobilization will continue through the weekend.
  4. Temporary enclosure will begin at rear accessible door.
  5. Saw cutting of the plaza near the rear accessible entrance will most likely begin the week of the 22nd. Prepare for loud noise, and medium level vibration.
  6. Trucking deliveries throughout the week.
  7. Installation of protection over entire Kemper surface as needed.

IMPACTS- High noise level from chipping, cutting, and grinding will be most noticeable north of building footprint

INTERIOR WORK: Week of 9/15/2025­

  1. Concrete repairs in mechanical room.
  2. Interior relocations for repairs in mechanical room
    IMPACTS- High noise level from cutting, chipping and grinding