GENERAL OCCUPANT INFORMATION
- The plaza renovation project is targeting an end of May 2026 completion date.
- Phase 1 high noise level work is scheduled to continue through October. Refer to TWLA schedule for further detail.
PLAZA WORK: Week of 9/15/2025
- Concrete repairs in west areaway continues.
- Concrete repairs in the mechanical room/basement.
- Scaffolding demobilization will continue through the weekend.
- Temporary enclosure will begin at rear accessible door.
- Saw cutting of the plaza near the rear accessible entrance will most likely begin the week of the 22nd. Prepare for loud noise, and medium level vibration.
- Trucking deliveries throughout the week.
- Installation of protection over entire Kemper surface as needed.
IMPACTS- High noise level from chipping, cutting, and grinding will be most noticeable north of building footprint
INTERIOR WORK: Week of 9/15/2025
- Concrete repairs in mechanical room.
- Interior relocations for repairs in mechanical room
IMPACTS- High noise level from cutting, chipping and grinding