The following summarizes the work planned at Eliot House during the week beginning Monday, September 15, 2025:
Dates: 09/22/25 – 09/28/25
PUBLIC WAY IMPACTS:
- Demo Trailer Trucking (maximum of 12 trailers a day) from Dunster Circle for the connector building demolition M-F. A laborer and an HUPD detail officer will be staged in the crosswalk in front of Kirland to help with pedestrian traffic.
EXTERIOR SITE ACTIVITIES:
- Demo of masonry banding around building.
- Exterior washing of masonry façade.
- Scaffold installation on the North building and chimneys in the SW.
- Demo / abatement of North building roof.
- Continuous daily dumpster swaps during first shift.
- Connector demolition at Dunster St.
INTERIOR ACTIVITIES:
- Saw cutting basement slabs.
- Drilling piles in basement.
- Demolition using lulls / trash chutes.
Weekend Activities:
- 09/20/25
- Demo / abatement of southwest building roof.
- Demo / abatement of Level 1 Southwest, Level 4 Northwest, abatement of Level 4 Southeast Eliot House.
- Setting Control L5.
- Demo of connector building.
- Patching / grouting roof gypsum.
WORK HOURS:
- Monday- Friday 7am-11pm (Two Shifts).
- Saturday 9am-5pm.