Week of September 22, 2025

The following summarizes the work planned at Eliot House during the week beginning Monday, September 15, 2025:​​​​​

Dates: 09/22/25 – 09/28/25

PUBLIC WAY IMPACTS:

  • Demo Trailer Trucking (maximum of 12 trailers a day) from Dunster Circle for the connector building demolition M-F. A laborer and an HUPD detail officer will be staged in the crosswalk in front of Kirland to help with pedestrian traffic.

EXTERIOR SITE ACTIVITIES:

  • Demo of masonry banding around building.
  • Exterior washing of masonry façade.
  • Scaffold installation on the North building and chimneys in the SW.
  • Demo / abatement of North building roof.
  • Continuous daily dumpster swaps during first shift.
  • Connector demolition at Dunster St.

INTERIOR ACTIVITIES:

  • Saw cutting basement slabs.
  • Drilling piles in basement.
  • Demolition using lulls / trash chutes.

Weekend Activities:

  • 09/20/25
    • Demo / abatement of southwest building roof.
    • Demo / abatement of Level 1 Southwest, Level 4 Northwest, abatement of Level 4 Southeast Eliot House.
    • Setting Control L5.
    • Demo of connector building.
    • Patching / grouting roof gypsum. 

WORK HOURS:

  • Monday- Friday 7am-11pm (Two Shifts).
  • Saturday 9am-5pm.