Week of September 29, 2025

The following summarizes the work planned at Eliot House during the week beginning Monday, September 29, 2025:​​​​​

Dates: 09/29/25 – 10/05/25

PUBLIC WAY IMPACTS:

  • Demo Trailer Trucking (maximum of 12 trailers a day) from Dunster Circle for the Connector building demolition on Monday. A laborer and HUPD will be staged in the crosswalk in front of Kirland to help with pedestrian traffic.

EXTERIOR SITE ACTIVITIES:

  • Demo of masonry banding around building.
  • Exterior washing of masonry façade.
  • Scaffold installation on the North building and chimneys in the SW.
  • Demo / abatement of North building roof.
  • Continuous daily dumpster swaps during first shift.
  • Connector demolition at Dunster St.
  • Pre-trenching for mass excavation at Dunster Circle.

INTERIOR ACTIVITIES:

  • Saw cutting basement slabs.
  • Drilling piles in basement.
  • Demolition using lulls / trash chutes.

Weekend Activities:

  • 9/27/25
    • Demo / abatement of Level 1 Southwest, Level 4 Northwest, Abatement of Level 4 Southeast Eliot House.
    • Demo of Connector building. 
    • Patching / grouting roof gypsum.
    • Scaffolding at Dunster Circle. 

WORK HOURS:

  • Monday- Friday 7am-11pm (Two Shifts).
  • Saturday 9am-5pm.