Week of October 20, 2025

The following summarizes the work planned for the new FAS building for the week of October 20, 2025:


Dates: 10/20/25 – 10/24/25

PUBLIC WAY IMPACTS:

  • Site fence will remain in its current location. Wayfinding signage has been installed around the site and at the Jefferson turnaround to assist vehicles, cyclists, pedestrians, and delivery drivers.

EXTERIOR SITE ACTIVITIES:

  • WL French will continue excavating along the interior of the secant pile wall and removing the concrete on the secant pile wall for the installation of bracing seats. Multiple trailers will be on site to haul out material from this operation. Noise and possible vibration impacts from this operation.
  • Treviicos will continue installing waler seats, walers and corner bracing on the interior of the secant pile wall. Noise impacts from this operation.

OTHER IMPACTS:

  • There will be multiple construction vehicles entering and existing the site. Equipment and trucking will continue using the construction entrance off Massachusetts Avenue between Gannett House and Hemenway Gymnasium in conjunction with the existing construction entrance onto Cambridge Street (between Gannett and Littauer).
  • The buildings and utilities are being monitored 24/7 for conformance with specified vibration tolerances.

WORK HOURS:

  • Monday 10/20/25 thru Friday 10/24/25 7:00 AM to 5:00 PM.
  • The project team will not be working after 4:00PM on 10/23/25 due to an event in the Ames Courtroom.
  • No work is currently planned for Saturday 10/25/25 at this time.