The following summarizes the work planned at Eliot House during the week beginning Monday, October 20, 2025:
Dates: 10/20/25 – 10/26/25
PUBLIC WAY IMPACTS:
- JFK Loading Dock. Hauling recycled materials. 2 Trucks Daily
- Dunster Street: Pile drilling; Generating 3-4 tri-axle truckloads of spoils every 2 days.
- Dunster Street: Pouring piles everyday (M-F) 10-12 BSG concrete trucks entering and exiting through Gate G on Dunster St. (Daily Street Sweeping)
EXTERIOR SITE ACTIVITIES:
- Demo of masonry banding around building.
- Exterior washing of masonry façade – South East Building
- Scaffold installation on the southeast building and Chimneys in the North
- Demo / abatement of South East roof.
- Continuous daily dumpster swaps during first shift off of Memorial Drive
- Drilling Piles in Dunster Circle
INTERIOR ACTIVITIES:
- Saw cutting Basement Slabs
- Drilling Piles in Basement
- Demolition using lulls / trash chutes.
- Removal of sub grade basement soils
- MEP Coring through Slabs
- Super Cap – Level 4
Weekend Activities:
- NO WEEKEND WORK DUE TO HOCR – 10/18/25 – 10/19/2025
WORK HOURS:
- Monday- Friday 7am-11pm (Two Shifts)
- Saturday: No Work