The following summarizes the work planned at 12 Palmer St for the week of October 20. Please note that items in BOLD are expected to generate some noticeable impacts.
Week of: 10/20/25 – 10/24/25
Temporary Public Way Impacts:
• There will be short-term deliveries on Palmer Street.
• There will be a crane pick on Wednesday 10/22. This will close Palmer Street and Bank of America parking.
Exterior Site Activities:
• Masons will be demoing brick above 32-42 Church Street which will
generate noise.
Interior Activities:
• There will be saw cutting on the first floor for 1 day.
Other Impacts:
• No other impacts are anticipated at this time.
Work Hours:
• Monday 10/20/25 – Friday 10/24/25 7:00 AM to 2:30 PM.
• No plan to work Saturday 10/25/25 at this time.