The following summarizes the work planned at Eliot House during the week beginning Monday, October 27, 2025:
Dates: 10/27/25 – 10/31/25
KIRKLAND HOUSE IMPACTS:
- Loading Dock: Demo contractor will continue loading debris from the connector demolition onto trailer dumps to haul offsite.
- Loading Dock / Connector: Demo contractor will continue with misc. demo to clean up debris and structural elements along the Kirkland Façade and dispose
- Dunster Street: Site contractor will continue with hauling materials in for backfill to support the drill rig for the Support of Excavation System. This will be multiple trailer dumps throughout the day.
- Dunster Street: Concrete trucks are scheduled throughout the week for the install of the Support of Excavation System.
- Dunster Street: Spoils from the drilling operation will be hauled off site towards the middle of next week utilizing Tri-Axels and/or Trailer Dumps.
- Dunster Street: Police Details have been scheduled to assist with pedestrian safety and vehicular traffic.
- Noisy work: Driving of piles for the support of excavation for the connector.
- Noisy Work: Eliot House Interior Demo Monday – Friday (7am – 6 pm) Saturday (9am – 5pm)
- Noisy Work: Eliot House Façade Restoration which includes masonry and roofing demolition
PUBLIC WAY IMPACTS:
- State Police Detail and HUPD detail called M-F to assist construction vehicles entering and exiting into public roads.
- Continuous deliveries off Memorial Drive into the courtyard.
EXTERIOR SITE ACTIVITIES:
- Demo of masonry banding around building.
- Exterior washing of masonry façade – Southeast Building
- Scaffold installation on the southeast building and Chimneys in the North
- Demo / abatement of Southeast roof.
- Continuous daily dumpster swaps during first shift off Memorial Drive
- Drilling Piles in Connector Area
- Demo of Chimneys on the North Building
- Rebuilding Chimneys on the southwest Building
INTERIOR ACTIVITIES:
- Saw cutting Basement Slabs
- Drilling Piles in Basement
- Demolition using lulls / trash chutes.
- Removal of sub grade basement soils
- MEP Coring through Slabs
- Concrete placement in the North Building
- Super Cap placement in the North Building
Weekend Activities:
10/25/25
- Demo / abatement of southeast building Level 3,2, Basement
- Scaffolding Erection at the Chimneys located on the roof by the JFK Loading Dock
- Façade Restoration by the Masons
WORK HOURS:
- Monday- Friday 7am-11pm (Two Shifts)
- Saturday 10/25/25 – 9am – 5pm