The following summarizes the work planned for the new FAS building for the week of November 3, 2025:
Dates: 11/3/25 – 11/7/25
PUBLIC WAY IMPACTS:
- The site fence will remain in its current location. Wayfinding signage has been installed around the site and at the Jefferson turnaround to assist vehicles, cyclists, pedestrians, and delivery drivers.
EXTERIOR SITE ACTIVITIES:
- WL French will continue removing the concrete on the secant pile wall for the installation of bracing seats. Noise and possible vibration impacts can be expected from this operation.
- Treviicos will continue installing waler seats, walers and corner bracing on the interior of the secant pile wall. Noise impacts can be anticipated from this operation.
- Keller will begin installing the mini-piles for the steam tunnel support work. Abutters can expect noise and possible vibration impacts from this operation.
- French will begin excavating inside the secant wall under the bracing. Multiple trailers will be on site for this operation. Some noise impacts from this work can be anticipated.
OTHER IMPACTS:
- There will be multiple construction vehicles entering and existing the site. Equipment and trucking will continue using the construction entrance off Massachusetts Avenue between Gannett House and Hemenway Gymnasium in conjunction with the existing construction entrance onto Cambridge Street (between Gannett and Littauer).
- The buildings and utilities are being monitored 24/7 for conformance with specified vibration tolerances.
WORK HOURS:
- Monday through Friday, November 3 -7 from 7:00 AM to 5:00 PM.
- There is no work planned for Saturday, November 8.