Week of November 17, 2025

The following summarizes the work planned for the new FAS building for the week of November 17, 2025:

Dates: 11/17/25 – 11/21/25
 
PUBLIC WAY IMPACTS:

  • The site fence will remain in its current location. Wayfinding signage has been installed around the site and at the Jefferson turnaround to assist vehicles, cyclists, pedestrians, and delivery drivers.

EXTERIOR SITE ACTIVITIES:

  • Treviicos will be working on welding miscellaneous bracing and railings around the site. Some noise impacts can be expected from this operation.
  • Keller will begin installing the mini-piles for the steam tunnel support work. Abutters can anticipate noise and possible vibration impacts from this operation.
  • French will begin excavating inside the secant wall under the bracing. Multiple trailers will be on site for this operation. There will be some noise impacts from this operation.

OTHER IMPACTS:

  • There will be multiple construction vehicles entering and existing the site. Equipment and trucking will continue using the construction entrance off Massachusetts Avenue between Gannett House and Hemenway Gymnasium in conjunction with the existing construction entrance onto Cambridge Street (between Gannett and Littauer).
  • The buildings and utilities are being monitored 24/7 for conformance with specified vibration tolerances.

WORK HOURS:

  • Monday through Friday, November 17 to 21, 7:00 AM to 5:00 PM.
  • There aren’t any plans to work Saturday, November 22, at this time.