The following summarizes the work planned at 12 Palmer St for the week of November 17. Please note that items in BOLD are expected to generate some noticeable impacts.
Week of: 11/17/25 – 11/21/25
Temporary Public Way Impacts:
- There will be a concrete pour on Tuesday 11/18/25.
- Bank of America parking will still be accessible.
- Sitework will continue on the Brattle side of Palmer St.
- There will be short term deliveries on Palmer St.
Exterior Site Activities:
- Masons will be demoing brick on the scaffolding and above 32-42 Church Street which will generate noise.
Interior Activities:
- No impactful interior activities are anticipated at this time.
Other Impacts:
- No other impacts are anticipated at this time.
Work Hours:
- Monday 11/17/25 – Friday 11/21/25 7:00 AM to 2:30 PM.