Week of December 1, 2025

The following summarizes the work planned at Eliot House during the week beginning Monday, December 1, 2025:​​​​​

Dates: 12/1/25-12/6/25

KIRKLAND HOUSE IMPACTS:

  • Dunster Street: Site Contractor will continue mass excavation and hauling out material.
  • Dunster Street: Police Details have been scheduled to assist with pedestrian safety and vehicular traffic.
  • Noisy Work: Site contractor will continue drilled pile operation.
  • Noisy Work: Eliot House Interior Demo Monday – Friday (7am – 3pm) Saturday (9am – 5pm).
  • Noisy Work: Eliot House Façade Restoration which includes masonry and roofing demolition.

PUBLIC WAY IMPACTS:

  • State Police Detail and HUPD detail called M-F to assist construction vehicles entering and exiting into public roads.
  • Continuous deliveries off Memorial Drive into the courtyard.

EXTERIOR SITE ACTIVITIES:

  • Demo of masonry banding around building.
  • Exterior washing of masonry façade – Southeast Building.
  • Scaffold installation on the chimneys in the North.
  • Demo / abatement of Southeast roof.
  • Continuous daily dumpster swaps during first shift off Memorial Drive.
  • Demo of chimneys on the North Building.
  • Rebuilding chimneys on the Southwest Building.
  • Mass excavation in Dunster Circle.
  • Site prep and drilled piles installation at Connector Building.

INTERIOR ACTIVITIES:

  • Saw cutting basement slabs.
  • Drilling piles in basement.
  • Demolition using lulls / trash chutes.
  • Removal of sub grade basement soils.
  • MEP coring through slabs.
  • Super cap placement in the North Building.
  • Framing and boarding in the Southwest Building.

WEEKEND ACTIVITIES:

Saturday – 12/6/25

  • Demo / abatement of Southeast Building – Level 1.
  • Rough carpentry for window blocking.
  • Site prep and drilling of piles at Connector – This will be a noisy activity.

WORK HOURS:

  • Monday-Friday 7am-6:00pm.
  • Saturday 12/6/25 – 9am – 5pm.