The following summarizes the work planned at Eliot House during the week beginning Monday, December 1, 2025:
Dates: 12/1/25-12/6/25
KIRKLAND HOUSE IMPACTS:
- Dunster Street: Site Contractor will continue mass excavation and hauling out material.
- Dunster Street: Police Details have been scheduled to assist with pedestrian safety and vehicular traffic.
- Noisy Work: Site contractor will continue drilled pile operation.
- Noisy Work: Eliot House Interior Demo Monday – Friday (7am – 3pm) Saturday (9am – 5pm).
- Noisy Work: Eliot House Façade Restoration which includes masonry and roofing demolition.
PUBLIC WAY IMPACTS:
- State Police Detail and HUPD detail called M-F to assist construction vehicles entering and exiting into public roads.
- Continuous deliveries off Memorial Drive into the courtyard.
EXTERIOR SITE ACTIVITIES:
- Demo of masonry banding around building.
- Exterior washing of masonry façade – Southeast Building.
- Scaffold installation on the chimneys in the North.
- Demo / abatement of Southeast roof.
- Continuous daily dumpster swaps during first shift off Memorial Drive.
- Demo of chimneys on the North Building.
- Rebuilding chimneys on the Southwest Building.
- Mass excavation in Dunster Circle.
- Site prep and drilled piles installation at Connector Building.
INTERIOR ACTIVITIES:
- Saw cutting basement slabs.
- Drilling piles in basement.
- Demolition using lulls / trash chutes.
- Removal of sub grade basement soils.
- MEP coring through slabs.
- Super cap placement in the North Building.
- Framing and boarding in the Southwest Building.
WEEKEND ACTIVITIES:
Saturday – 12/6/25
- Demo / abatement of Southeast Building – Level 1.
- Rough carpentry for window blocking.
- Site prep and drilling of piles at Connector – This will be a noisy activity.
WORK HOURS:
- Monday-Friday 7am-6:00pm.
- Saturday 12/6/25 – 9am – 5pm.