Week of December 22, 2025

The following summarizes the work planned at 12 Palmer St for the week of December 22. Please note that items in BOLD are expected to generate some noticeable impacts. 

Week Of: 12/22/25 – 12/26/25

Temporary Public Way Impacts:

  • A concrete pour will be scheduled for Wednesday, December 24 or Friday, December 26. A pump truck will be set up in the street during the construction work hours. Harvard Construction Mitigation will provide an update when the road closure is officially scheduled.
    • Palmer street and Bank of America parking will be closed during this time.
  • A brick delivery is scheduled for Monday morning on December 22. Machinery will be used to unload the material. This will result in a short-term road closure.
    • A spotter will be used at all times to monitor pedestrian traffic.
    • Bank of America parking will still be accessible.

Exterior Site Activities:

  • Masons will be demoing brick on the scaffolding and above 32-42 Church Street which will generate noise.

Interior Activities:

  • No impactful interior activities are anticipated at this time.

Other Impacts:

  •  No other impacts are anticipated at this time.

Work Hours:

  • Monday – Wednesday and Friday from 7:00 AM to 2:30 PM.
  • The jobsite will be closed on Thursday, December 25 due to the Christmas Holiday.