The following summarizes the work planned at 12 Palmer St for the week of January 12. Please note that items in BOLD are expected to generate some noticeable impacts. 

Week of: 1/12/26 – 1/16/26

Temporary Public Way Impacts:

  • A crane pick is scheduled for Wednesday, January 14. The crane will arrive first thing in the morning to hoist mechanical units to the roof.
    • Palmer Street and Bank of America parking will be closed for the entire day.

Exterior Site Activities:

  • Masons will be installing brick on the scaffolding to the left of the bridges which will generate noise.

Interior Activities:

  • No impactful interior activities are anticipated at this time.

Other Impacts:

  • No other impacts are anticipated at this time.

Work Hours:

  • Monday 1/12/26 – Friday 1/16/26 7:00 AM to 2:30 PM.
  • Saturday 1/17/26 no work is planned.