Public Way Impacts
- Harvard/Cambridge Police details will be posted at each intersection of Bow Street, Linden Street and Plympton Street.
 - Bow Street will remain closed in front of Randolph Hall from Linden to Plympton Street.
 - Linden Street and Plympton Street will have a drive lane and both roads will remain open for pedestrians.
 - Linden Street will periodically be blocked to vehicle traffic for dumpster swaps, deliveries, and to move machinery.
 - A site fence has been installed, including lighting and signage.
 - Dumpster swaps will continue at the north end of Plympton Street, Bow Street, and the courtyard.
 - Continuous deliveries will happen at Linden, Plympton, and Bow Streets.
 - The Tower Crane located in the courtyard will be active from 7:00 AM – 3:00 PM daily.
 
Exterior Site Activities
- Work on the dormers will occur in the courtyard.
 - Façade work will continue.
 - Roof slate and flashing will be installed in the courtyard.
 - Stonework will continue to take place.
 - Dumpster loading with trash chute will continue on Bow Street.
 - Deliveries will be made on Bow Street for load-in of material at southwest gate as well as on Linden Street at the entrance to the Courtyard.
 
Interior Site Activities
- Miscellaneous demo work will go on as needed.
 - Backfilling for the foundation will continue.
 - Fire proofing will take place.
 - Windows will continue to be installed.
 - The 1st and 2nd floor will be taped and plastered.
 - Work on the foundation in the basement will occur.
 - Framing will take place on the 1st floor.
 - Sheetrocking will continue to be installed on the 3rd floor as well as painting.
 - Installation of risers for electrical, plumbing, mechanical, and fire protection will continue, as well as overhead rough-ins.