Week of January 6, 2025

The following summarizes the utility work planned in the Littauer Lot for the week of January 6 Please note that items in BOLD are expected to generate some noticeable noise.

Dates: 1/6/25-1/10/25

PUBLIC WAY IMPACTS:

  • Fencing will remain relocated in Phase 2B/2C.  

EXTERIOR SITE ACTIVITIES: 

  • Excavation will continue at the Littauer Entrance. Noise impact from excavation operation.
  • Excavation will continue for temporary transformer duct banks and pads in front of Austin Hall. Noise impact from excavation operation.
  • Backfill and restoration will begin at the Littauer tie-in area. Noise and vibration impact from backfilling and paving operations. 
  • Conduit installation will begin from the Littauer tie-in towards the Littauer Entrance. 
  • Excavation will begin for the installation of a manhole structure. Noise and vibration impact from excavation and backfilling operations.

OTHER IMPACTS:

  • Concrete placement at Littauer tie-in.
  • Soil sampling will continue on Monday, January 6 through Friday, January 10. The areas to be sampled are within the proposed site and current work area. Noise and vibration impacts can be anticipated from sampling.

WORK HOURS:

  • Monday-Friday 7:00 AM to 3:30 PM.  
  • Tentative plan to work Saturday, January 11 from 9:00 AM to 4:00 PM to maintain schedule.