Week of June 16, 2025

Week of: 6/16/25 – 6/20/25

Temporary Public Way Impacts:

• The abatement subcontractor will be loading out CMU waste throughout the week. There will be temporary Palmer Street impacts (15-30 minutes) to remove the dumpsters.

Exterior Site Activities:

• No major exterior activities are scheduled for next week.

Interior Activities:

• Concrete chipping/demo activities ongoing on the interior of the building.

Other Impacts:

• No other impacts are expected.

Work Hours:

• The jobsite will be open on the Juneteenth holiday from 9:00 AM to 6:00 PM.

• Monday – Wednesday, Friday 7:00 AM to 2:30 PM.

• No plan to work Saturday, June 21 at this time.