The following summarizes the work planned at 12 Palmer St for the week of August 11. Please note that items in BOLD are expected to generate some noticeable impacts.
Week of: 8/11/25 – 8/15/25
Public Way Impacts:
• Palmer Street will have a temporary road closure on Tuesday, 8/12/25, from 7 am – 2 pm for a crane pick. Police details will be in place to prevent vehicle and pedestrian traffic from entering Palmer Street. This closure will also impact the Bank of America parking.
• There will be a 1-2 hour concrete delivery on Wednesday 8/13/25.
Exterior Site Activities:
• On Thursday 8/14/25, there will be ongoing work on the exterior scaffolding.
Interior Activities:
• Concrete saw cutting will be ongoing in the basement of the building. This may create some noise/vibrations
Other Impacts:
• No other impacts are anticipated.
Work Hours:
• Monday 8/11/25 – Friday 8/15/25 7:00 AM to 2:30 PM.
• No plan to work Saturday 8/16/25 at this time.