The following summarizes the work planned at Eliot House during the week beginning Monday, September 2, 2025:
Dates: 09/02/25 – 09/07/25
PUBLIC WAY IMPACTS:
- None
EXTERIOR SITE ACTIVITIES:
- Demo of masonry banding around building.
- Exterior washing of masonry façade.
- Scaffold installation on the North building and chimneys in the SW.
- Demo / abatement of North building roof.
- Continuous daily dumpster swaps during first shift.
- Connector demolition at Dunster St.
INTERIOR ACTIVITIES:
- Saw cutting Basement Slabs.
- Drilling piles in basement.
- Demolition using lulls / trash chutes.
Weekend Activities:
- 09/06/25
- Demo / abatement of southwest building roof.
- Demo / abatement Eliot House.
- Scaffolding at JFK.
 
WORK HOURS:
- Monday- Friday 7am-11pm (Two Shifts).
- Saturday 9am-5pm.