Week of September 8, 2025

The following summarizes the work planned at Eliot House during the week beginning Monday, September 8, 2025:​​​​​

Dates: 09/08/25 – 09/14/25

PUBLIC WAY IMPACTS:

  • None

EXTERIOR SITE ACTIVITIES:

  • Demo of masonry banding around building.
  • Exterior washing of masonry façade.
  • Scaffold installation on the North building and Chimneys in the SW.
  • Demo / abatement of North building roof.
  • Continuous daily dumpster swaps during first shift.
  • Connector Demolition at Dunster St.

INTERIOR ACTIVITIES:

  • Saw cutting Basement Slabs
  • Drilling Piles in Basement
  • Demolition using lulls / trash chutes.

Weekend Activities:

  • 09/06/25
    • Demo / abatement of southwest building roof
    • Demo / abatement Eliot House.
    • Scaffolding at JFK.

WORK HOURS:

  • Monday- Friday 7am-11pm (Two Shifts)
  • Saturday 9am-5pm