The following summarizes the work planned at 12 Palmer St for the week of November 24. Please note that items in BOLD are expected to generate some noticeable impacts.
Week of: 11/24/25 – 11/28/25
Temporary Public Way Impacts:
- A crane is scheduled for Tuesday 11/25/25.
- Palmer street and Bank of America parking will be closed.
- A crane is scheduled for Friday 11/28/25.
- Palmer street and Bank of America parking will be closed.
- There will be short term deliveries on Palmer St.
Exterior Site Activities:
- Masons will be demoing brick on the scaffolding and above 32-42 Church Street which will generate noise.
Interior Activities:
- No impactful interior activities are anticipated at this time.
Other Impacts:
- No other impacts are anticipated at this time.
Work Hours:
- Monday 11/24/25 – Friday 11/28/25 7:00 AM to 2:30 PM.
- No plan to work Saturday 11/29/25 at this time.