Week of November 24, 2025

GENERAL OCCUPANT INFORMATION

  • Work will be within designated construction areas unless noted otherwise. Project work hours will be Monday through Friday from 7:00 a.m. to 3:30 p.m.
    Some Saturday work between 7:00 a.m. and 4:00 p.m. by permit may be necessary, with noisy work after 9:00 AM
  • The plaza renovation project is targeting an end of May 2026 completion date.
  • Construction parking spots will be moved to accommodate work.
  • Phase 1 high noise level work is scheduled to continue into November.

PLAZA WORK: Week of 11/25/25

  1. Concrete Repairs in west areaway continues.
  2. Trucking deliveries throughout the week.
  3. Perimeter soffit work around the exterior of the building will continue the week of 11/24/25 (Weather Depending).
  4. Use of lull on Kirkland Street Plaza will be ongoing during week of 11/24/25.
  5. North sidewalk structural repairs will be ongoing the week of 11/24/25.
  6. Scaffolding enclosure work will continue at the east side of the plaza during the week of 11/24/25.    
  7. Bike racks will be temporarily relocated adjacent to Divinity Ave. west of WJH planter.                                                                 

IMPACTS– high noise level from chipping, cutting, and grinding will be most noticeable in the north of the building footprint.

INTERIOR WORK: Week of 11/25/25

  1. Concrete repairs in mechanical room.
  2. Interior relocations for repairs in mechanical room.
  3. MEP hanger installation in the mechanical room will occur during the week of 11/24/25.
  4. Removal of ceilings in basement.

IMPACTS- medium noise level from cutting, chipping, and grinding.