The following summarizes the work planned at 12 Palmer St for the week of January 26. Please note that items in BOLD are expected to generate some noticeable impacts. Week of: 1/26/26 – 1/30/26 Temporary Public Way Impacts: Exterior Site Activities: Interior Activities: Other Impacts: Work Hours:…Continue Reading Week of January 26, 2026
Week of January 19, 2026
The following summarizes the work planned at 12 Palmer St for the week of January 19. Please note that items in BOLD are expected to generate some noticeable impacts. Week of: 1/19/26 – 1/23/26 Temporary Public Way Impacts: Exterior Site Activities: Interior Activities: Other Impacts: Work Hours:…Continue Reading Week of January 19, 2026
Week of January 12, 2026
The following summarizes the work planned at 12 Palmer St for the week of January 12. Please note that items in BOLD are expected to generate some noticeable impacts. Week of: 1/12/26 – 1/16/26 Temporary Public Way Impacts: Exterior Site Activities: Interior Activities: Other Impacts: Work Hours:…Continue Reading Week of January 12, 2026
Week of January 5, 2026
The following summarizes the work planned at 12 Palmer St for the week of January 5. Please note that items in BOLD are expected to generate some noticeable impacts. Week of: 1/5/26 – 1/9/26 Temporary Public Way Impacts: Exterior Site Activities: Interior Activities: Other Impacts: Work Hours:…Continue Reading Week of January 5, 2026
Week of December 22, 2025
The following summarizes the work planned at 12 Palmer St for the week of December 22. Please note that items in BOLD are expected to generate some noticeable impacts. Week Of: 12/22/25 – 12/26/25 Temporary Public Way Impacts: Exterior Site Activities: Interior Activities: Other Impacts: Work Hours:…Continue Reading Week of December 22, 2025
Week of December 15, 2025
The following summarizes the work planned at 12 Palmer St for the week of December 15. Please note that items in BOLD are expected to generate some noticeable impacts. Week of: 12/15/25 – 12/19/25 Temporary Public Way Impacts: Exterior Site Activities: Interior Activities: Other Impacts: Work Hours:…Continue Reading Week of December 15, 2025
Week of December 8, 2025
Week of: 12/8/25 – 12/12/25 Temporary Public Way Impacts:• A concrete pour on the roof will be scheduled for mid/late next week depending on the weather conditions. This concrete pour will require a pump truck and a full day road closure. (7am-2pm)o Once the date is finalized, a notice will be sent to the neighbors.o Bank…Continue Reading Week of December 8, 2025
Week of December 1, 2025
The following summarizes the work planned at 12 Palmer St for the week of December 1. Please note that items in BOLD are expected to generate some noticeable impacts. Week of: 11/27/25 – 12/5/25 Temporary Public Way Impacts: Exterior Site Activities: Interior Activities: Other Impacts: Work Hours:…Continue Reading Week of December 1, 2025
Week of November 24, 2025
The following summarizes the work planned at 12 Palmer St for the week of November 24. Please note that items in BOLD are expected to generate some noticeable impacts. Week of: 11/24/25 – 11/28/25 Temporary Public Way Impacts: Exterior Site Activities: Interior Activities: Other Impacts: Work Hours:…Continue Reading Week of November 24, 2025
Week of November 17, 2025
The following summarizes the work planned at 12 Palmer St for the week of November 17. Please note that items in BOLD are expected to generate some noticeable impacts. Week of: 11/17/25 – 11/21/25 Temporary Public Way Impacts: Exterior Site Activities: Interior Activities: Other Impacts: Work Hours:…Continue Reading Week of November 17, 2025