Week of June 23, 2025

The following summarizes the work planned at 12 Palmer St for the week of June 23. Please note that items in BOLD are expected to generate some noticeable impacts.  Week of: 6/23/25 – 6/27/25 Public Way Impacts: • No major public way impacts. Exterior Site Activities: • The sitework contractor will be removing pavers within the fence…Continue Reading Week of June 23, 2025

Week of June 16, 2025

Week of: 6/16/25 – 6/20/25 Temporary Public Way Impacts: • The abatement subcontractor will be loading out CMU waste throughout the week. There will be temporary Palmer Street impacts (15-30 minutes) to remove the dumpsters. Exterior Site Activities: • No major exterior activities are scheduled for next week. Interior Activities: • Concrete chipping/demo activities ongoing…Continue Reading Week of June 16, 2025

Week of June 9, 2025

The following summarizes the work planned at 12 Palmer St for the week of June 9. Please note that items in BOLD are expected to generate some noticeable impacts.  Week of: 6/9/25 – 6/13/25 Temporary Public Way Impacts: • The abatement subcontractor will be loading out CMU waste throughout the week. There will be temporary Palmer Street…Continue Reading Week of June 9, 2025

Week of May 12, 2025

The following summarizes the work planned at 12 Palmer St for the week of May 12. Please note that items in BOLD are expected to generate some noticeable noise.  Week Of: 5/12/25 – 5/16/25Public Way Impacts:•    Scaffolding delivery will be scheduled this week, date TBD.•    No major road closures are anticipated. Exterior Site Activities: •    Masons will be…Continue Reading Week of May 12, 2025

Week of May 19, 2025

The following summarizes the work planned at 12 Palmer St for the week of May 19. Please note that items in BOLD are expected to generate some noticeable noise.  Week Of: 5/19/25 – 5/23/25Public Way Impacts:• No Consigli road closures are anticipated.• We have been told that Bank of America is expecting to close Palmerstreet for a…Continue Reading Week of May 19, 2025

Week of May 5, 2025

The following summarizes the work planned at 12 Palmer St for the week of May 5. Please note that items in BOLD are expected to generate some noticeable noise.  Dates: 5/05/25 – 5/10/25 Public Way Impacts: • Short-term scaffolding delivery will be on Monday, May 5.   • No major road closures are anticipated. Exterior Site Activities:…Continue Reading Week of May 5, 2025