The following summarizes the work planned for the New FAS Building for the week of July 21. Please note that items in BOLD are expected to generate some noticeable noise or impacts. Dates: 7/21/25-7/25/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: OTHER IMPACTS: WORK HOURS:…Continue Reading Week of July 21, 2025
Week of July 14, 2025
The following summarizes the work planned at 12 Palmer St for the week of July 14. Please note that items in BOLD are expected to generate some noticeable impacts. Week of: 7/14/25 – 7/18/25 Public Way Impacts: • No major public way impacts are expected Exterior Site Activities: • A compressor will be running during work hours…Continue Reading Week of July 14, 2025
Week of July 7, 2025
The following summarizes the work planned at 12 Palmer St for the week of July 7. Please note that items in BOLD are expected to generate some noticeable impacts. Week of: 7/7/25 – 7/11/25 Public Way Impacts: • The steel subcontractor will have a short-term steel delivery on Monday morning, July 7. • No other major public…Continue Reading Week of July 7, 2025
Week of June 30, 2025
The following summarizes the work planned at 12 Palmer St for the week of June 30. Please note that items in BOLD are expected to generate some noticeable impacts. Week of: 6/30/25 – 7/3/25 Public Way Impacts: • A vac truck will be used to excavate for the Eversource conduits on 7/1. The truck will be set…Continue Reading Week of June 30, 2025
Week of June 23, 2025
The following summarizes the work planned at 12 Palmer St for the week of June 23. Please note that items in BOLD are expected to generate some noticeable impacts. Week of: 6/23/25 – 6/27/25 Public Way Impacts: • No major public way impacts. Exterior Site Activities: • The sitework contractor will be removing pavers within the fence…Continue Reading Week of June 23, 2025
Week of June 16, 2025
Week of: 6/16/25 – 6/20/25 Temporary Public Way Impacts: • The abatement subcontractor will be loading out CMU waste throughout the week. There will be temporary Palmer Street impacts (15-30 minutes) to remove the dumpsters. Exterior Site Activities: • No major exterior activities are scheduled for next week. Interior Activities: • Concrete chipping/demo activities ongoing…Continue Reading Week of June 16, 2025
Week of June 9, 2025
The following summarizes the work planned at 12 Palmer St for the week of June 9. Please note that items in BOLD are expected to generate some noticeable impacts. Week of: 6/9/25 – 6/13/25 Temporary Public Way Impacts: • The abatement subcontractor will be loading out CMU waste throughout the week. There will be temporary Palmer Street…Continue Reading Week of June 9, 2025
Week of June 2, 2025
The following summarizes the work planned at 12 Palmer St for the week of June 2. Please note that items in BOLD are expected to generate some noticeable impacts. Dates: 06/02/25-06/07/25 Public Way Impacts: Exterior Site Activities: Interior Activities: Other Impacts: Work Hours:…Continue Reading Week of June 2, 2025
Week of May 27, 2025
The following summarizes the work planned at 12 Palmer St for the week of May 27. Please note that items in BOLD are expected to generate some noticeable impacts. Dates: 5/27/25-5/30/25Public Way Impacts: Exterior Site Activities: Interior Activities: Other Impacts: Work Hours:…Continue Reading Week of May 27, 2025
Week of May 12, 2025
The following summarizes the work planned at 12 Palmer St for the week of May 12. Please note that items in BOLD are expected to generate some noticeable noise. Week Of: 5/12/25 – 5/16/25Public Way Impacts:• Scaffolding delivery will be scheduled this week, date TBD.• No major road closures are anticipated. Exterior Site Activities: • Masons will be…Continue Reading Week of May 12, 2025