The following summarizes the work planned at 12 Palmer St for the week of October 13. Please note that items in BOLD are expected to generate some noticeable impacts. Week of: 10/13/25 – 10/17/25 Temporary Public Way Impacts:• There will be short-term deliveries on Palmer Street.• Eversource will have a crew excavating for underground conduits onPalmer Street…Continue Reading Week of October 13, 2025
Week of October 6, 2025
The following summarizes the work planned at 12 Palmer St for the week of October 6. Please note that items in BOLD are expected to generate some noticeable impacts. Week of: 10/6/25 – 10/10/25 Temporary Public Way Impacts:• There will be short-term deliveries on Palmer Street. Exterior Site Activities:• Masons will be demoing brick above 32-42 Church Street which…Continue Reading Week of October 6, 2025
Week of September 29, 2025
The following summarizes the work planned at 12 Palmer St for the week of September 29. Please note that items in BOLD are expected to generate some noticeable impacts. Week of: 9/29/25 – 10/3/25 Temporary Public Way Impacts: Exterior Site Activities: Other Impacts: Work Hours:…Continue Reading Week of September 29, 2025
Week of September 22, 2025
The following summarizes the work planned at 12 Palmer St for the week of September 22. Please note that items in BOLD are expected to generate some noticeable impacts. Week of: 9/22/25 – 9/26/25 Temporary Public Way Impacts: Exterior Site Activities: Interior Activities: Other Impacts: Work Hours:…Continue Reading Week of September 22, 2025
Week of September 15, 2025
The following summarizes the work planned at 12 Palmer St for the week of September 15. Please note that items in BOLD are expected to generate some noticeable impacts. Week of: 9/15/25 – 9/19/25Temporary Public Way Impacts:• There will be short-term deliveries on Palmer Street.Exterior Site Activities:• Masons will be demoing brick on the exterior of the…Continue Reading Week of September 15, 2025
Week of September 8, 2025
The following summarizes the work planned at 12 Palmer St for the week of September 8. Please note that items in BOLD are expected to generate some noticeable impacts. Week Of: 9/8/25 – 9/12/25Temporary Public Way Impacts:• Road closure tentatively scheduled for Wednesday 9/10/25 for a crane pick.• There will be short-term deliveries on Palmer Street.Exterior Site…Continue Reading Week of September 8, 2025
Week of September 2, 2025
The following summarizes the work planned at 12 Palmer St for the week of September 2. Please note that items in BOLD are expected to generate some noticeable impacts. Week of: 9/2/25 – 9/5/25 Temporary Public Way Impacts:• Palmer Street road closure on Thursday 9/4/25 for a crane pick.• Palmer Street road closure on Friday 9/5/25 for…Continue Reading Week of September 2, 2025
Week of August 25, 2025
The following summarizes the work planned at 12 Palmer St for the week of August 25. Please note that items in BOLD are expected to generate some noticeable impacts. Week of: 8/25/25 – 8/29/25 Temporary Public Way Impacts:• There will be short-term deliveries on Palmer Street.• No major impacts are anticipated.Exterior Site Activities:• There will be a…Continue Reading Week of August 25, 2025
Week of August 18 2025
The following summarizes the work planned at 12 Palmer St for the week of August 18. Please note that items in BOLD are expected to generate some noticeable impacts. Week of: 8/18/25 – 8/22/25Temporary Public Way Impacts:• There will be short-term deliveries on Palmer Street.• No major impacts are anticipated.Exterior Site Activities:• The sitework subcontractor will have…Continue Reading Week of August 18 2025
Week of August 11, 2025
The following summarizes the work planned at 12 Palmer St for the week of August 11. Please note that items in BOLD are expected to generate some noticeable impacts. Week of: 8/11/25 – 8/15/25Public Way Impacts:• Palmer Street will have a temporary road closure on Tuesday, 8/12/25, from 7 am – 2 pm for a crane pick….Continue Reading Week of August 11, 2025