The following summarizes the work planned at 12 Palmer St for the week of December 1. Please note that items in BOLD are expected to generate some noticeable impacts. Week of: 11/27/25 – 12/5/25 Temporary Public Way Impacts: Exterior Site Activities: Interior Activities: Other Impacts: Work Hours:…Continue Reading Week of December 1, 2025
Week of November 24, 2025
The following summarizes the work planned at 12 Palmer St for the week of November 24. Please note that items in BOLD are expected to generate some noticeable impacts. Week of: 11/24/25 – 11/28/25 Temporary Public Way Impacts: Exterior Site Activities: Interior Activities: Other Impacts: Work Hours:…Continue Reading Week of November 24, 2025
Week of November 17, 2025
The following summarizes the work planned at 12 Palmer St for the week of November 17. Please note that items in BOLD are expected to generate some noticeable impacts. Week of: 11/17/25 – 11/21/25 Temporary Public Way Impacts: Exterior Site Activities: Interior Activities: Other Impacts: Work Hours:…Continue Reading Week of November 17, 2025
Week of November 3, 2025
The following summarizes the work planned at 12 Palmer St for the week of November 3. Please note that items in BOLD are expected to generate some noticeable impacts. Week of: 11/3/25 – 11/7/25 Temporary Public Way Impacts: Exterior Site Activities: Interior Activities: Work Hours:…Continue Reading Week of November 3, 2025
Week of October 20, 2025
The following summarizes the work planned at 12 Palmer St for the week of October 20. Please note that items in BOLD are expected to generate some noticeable impacts. Week of: 10/20/25 – 10/24/25 Temporary Public Way Impacts:• There will be short-term deliveries on Palmer Street.• There will be a crane pick on Wednesday 10/22. This will…Continue Reading Week of October 20, 2025
Week of October 13, 2025
The following summarizes the work planned at 12 Palmer St for the week of October 13. Please note that items in BOLD are expected to generate some noticeable impacts. Week of: 10/13/25 – 10/17/25 Temporary Public Way Impacts:• There will be short-term deliveries on Palmer Street.• Eversource will have a crew excavating for underground conduits onPalmer Street…Continue Reading Week of October 13, 2025
Week of October 6, 2025
The following summarizes the work planned at 12 Palmer St for the week of October 6. Please note that items in BOLD are expected to generate some noticeable impacts. Week of: 10/6/25 – 10/10/25 Temporary Public Way Impacts:• There will be short-term deliveries on Palmer Street. Exterior Site Activities:• Masons will be demoing brick above 32-42 Church Street which…Continue Reading Week of October 6, 2025
Week of September 29, 2025
The following summarizes the work planned at 12 Palmer St for the week of September 29. Please note that items in BOLD are expected to generate some noticeable impacts. Week of: 9/29/25 – 10/3/25 Temporary Public Way Impacts: Exterior Site Activities: Other Impacts: Work Hours:…Continue Reading Week of September 29, 2025
Week of September 22, 2025
The following summarizes the work planned at 12 Palmer St for the week of September 22. Please note that items in BOLD are expected to generate some noticeable impacts. Week of: 9/22/25 – 9/26/25 Temporary Public Way Impacts: Exterior Site Activities: Interior Activities: Other Impacts: Work Hours:…Continue Reading Week of September 22, 2025
Week of September 15, 2025
The following summarizes the work planned at 12 Palmer St for the week of September 15. Please note that items in BOLD are expected to generate some noticeable impacts. Week of: 9/15/25 – 9/19/25Temporary Public Way Impacts:• There will be short-term deliveries on Palmer Street.Exterior Site Activities:• Masons will be demoing brick on the exterior of the…Continue Reading Week of September 15, 2025