The following summarizes the work planned for the new FAS building for the week of August 11, 2025: Dates: 8/11/25-8/15/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: OTHER IMPACTS: WORK HOURS:…Continue Reading Week of August 11, 2025
Week of August 4, 2025
The following summarizes the work planned for the new FAS building for the week of August 4, 2025: PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: OTHER IMPACTS: WORK HOURS:…Continue Reading Week of August 4, 2025
Week of July 28, 2025
The following summarizes the work planned for the new FAS building for the week of July 28: PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: OTHER IMPACTS: WORK HOURS:…Continue Reading Week of July 28, 2025
Week of July 21, 2025
The following summarizes the work planned for the New FAS Building for the week of July 21. Please note that items in BOLD are expected to generate some noticeable noise or impacts. Dates: 7/21/25-7/25/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: OTHER IMPACTS: WORK HOURS:…Continue Reading Week of July 21, 2025
Week of July 14, 2025
The following summarizes the work planned for the New FAS Building for the week of July 14. Please note that items in BOLD are expected to generate some noticeable noise or impacts. Dates: 7/14/25-7/18/25PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: OTHER IMPACTS: WORK HOURS:…Continue Reading Week of July 14, 2025
Week of July 7, 2025
The following summarizes the work planned for the New FAS Building for the week of July 7. Please note that items in BOLD are expected to generate some noticeable noise or impacts. Dates: 7/7/25-7/11/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: OTHER IMPACTS: WORK HOURS:…Continue Reading Week of July 7, 2025
Week of June 30, 2025
The following summarizes the work planned for the New FAS Building for the week of June 30. Please note that items in BOLD are expected to generate some noticeable noise or impacts. Dates: 6/30/25-7/4/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: OTHER IMPACTS: WORK HOURS:…Continue Reading Week of June 30, 2025
Week of June 23, 2025
The following summarizes the work planned for the New FAS Building for the week of June 23. Please note that items in BOLD are expected to generate some noticeable noise or impacts. Dates: 6/23/25-6/27/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: OTHER IMPACTS: WORK HOURS:…Continue Reading Week of June 23, 2025
Week of June 16, 2025
Dates: 6/16/25-6/20/25 PUBLIC WAY IMPACTS: EXTERIOR SITE ACTIVITIES: OTHER IMPACTS: WORK HOURS:…Continue Reading Week of June 16, 2025