Public Way Impacts
- Harvard/Cambridge Police details will be posted at each intersection of Bow Street, Linden Street and Plympton Street.
- Bow Street will remain closed in front of Randolph Hall from Linden to Plympton Street.
- Linden Street and Plympton Street will periodically be blocked to vehicle traffic for dumpster swaps, deliveries, and to move machinery.
- A site fence has been installed, including lighting and signage.
- Dumpster swaps will continue at the north end of Plympton Street, Bow Street, and the courtyard.
- Continuous deliveries will happen at Linden, Plympton, and Bow Streets.
Exterior Site Activities
- Work on the courtyard landscape and hardscape is progressing.
- Sidewalk curbing on Linden Street continues to be set with no impacts.
- Exterior doors will continue to be set.
Interior Site Activities
- Punch list items will continue to occur on the 1st, 2nd, and 3rd floors.
- Spray insulation on the ground floor remains ongoing.
- Taping, plastering, and finishing will occur on the ground floor.
- Tile installation is continuing on the 1st and ground floor.
- Wood flooring continues to be installed on the 1st floor.
- Installation of trim will continue to take place on the 1st floor.
- Priming and applying the first coat of paint is ongoing.
- Application of finish paint will occur where applicable.
- Restoration of the stairs is progressing.
- Window shades will continue to be installed.
- Appliances, toilet accessories, bathroom mirrors, door handles, and additional hardware will continue to be installed.
- Overhead rough-ins for electrical, plumbing, mechanical, Tel data, and fire protection continues.