The following summarizes the work planned on the Adams House Phase 3 renovation for the week of September 25. Please note that items in BOLD are expected to generate some noticeable noise.

PUBLIC WAY IMPACTS:

  1. Continuous deliveries and dumpster swaps throughout the week.
  2. Load out from back parking lot and live load of dumpsters on Bow Street will continue.
  3. Drainage tie-in at Arrow Street will start. Work will begin within the site fence during the middle of the week. 
  4. Work outside the site fence will be coordinated with Cambridge DPW. 

EXTERIOR SITE ACTIVITIES:

  1. Masonry work on the exterior façade will continue.
  2. Roofing abatement at Westmorly will continue.
  3. A crane will be within the site fence, by Lower Bow Street, to support demolition work.
  4. Man/material hoist will be operating while the site is open.
  5. On weekdays the lift will operate until 6:00pm.

INTERIOR ACTIVITIES:

  1. Interior rough carpentry will continue.
  2. Abatement will continue inside Westmorly and Russell Hall.
  3. Interior demolition of Westmorly and Russell Hall.

WORK HOURS:

  1. Monday to Friday: 7:00am to 3:30pm with second shifts from 3:30pm to 10:30pm (No exterior noise after 6pm)
  2. Saturday 9/30 – 9:00am to 4:30pm