Day: October 6, 2023

Week of October 9, 2023

The Western Avenue utility crossing roadway work is finalized and is extending onto Kresge Way. This work will continue into fall 2023 and is being coordinated with University operations.   Kresge Way Temporary Relocation As part of Harvard’s infrastructure improvements in Allston, the University has extended thermal piping and electrical/telecommunications duct banks from the District Energy Facility across Western…Continue Reading Week of October 9, 2023