The following summarizes the work planned on the Adams House Phase 3 renovation for the week of November 6. Please note that items in BOLD are expected to generate some noticeable noise.
PUBLIC WAY IMPACTS:
- Continuous deliveries and dumpster swaps throughout the week.
- Crew will be live loading demo debris from the back parking lot to a dumpster staged on Bow Street.
- Eversource is scheduled to remove the existing gas main at the intersection of Bow Street and Arrow Street on Monday 11/6 and Tuesday 11/7.
- This is an Eversource project and is permitted separately from the Adams Phase 3 Project.
- Following this work crews will complete a storm drain tie-in in this area.
- Jersey barriers along upper Bow Street will be reinstalled following this work.
EXTERIOR SITE ACTIVITIES:
- Masonry work on the exterior façade will continue.
- Scaffolding installation will continue along the west, south and east elevations of Westmorly Hall.
- Man/material hoist will be operating while the site is open.
- On weekdays the lift will operate 7:00am-5:00pm and Saturday it will operation from 9:00am-4:30pm.
- Steel erection at the fourth floor of Westmorly Hall will continue.
- Dewatering equipment will be delivered to the site to begin the dewatering process.
- Crews will make the final connections for temporary heating equipment and a gas meter in the alley between Adams House and 22 Plympton Street.
INTERIOR ACTIVITIES:
- Interior rough carpentry will continue.
- Interior demolition of Westmorly and Russell Halls.
- Steel erection within Westmorly Hall will continue.
- Saw cutting and removal of Russell Hall slab will continue.
WORK HOURS:
- Monday to Friday: 7:00am to 3:30pm
Saturday 11/11 – Site will be closed due to Veterans Day