The following summarizes the work planned on the Adams House Phase 3 renovation for the week of November 20. Please note that items in BOLD are expected to generate some noticeable noise.
PUBLIC WAY IMPACTS:
- Continuous deliveries and dumpster swaps throughout the week.
- Crew will be live loading demo debris from the back parking lot to a dumpster staged on Bow Street.
- Stormwater system tie-in work will begin on Monday, November 20th, at the intersection of Bow Street and Arrow Street.
- This work will continue throughout the week.
EXTERIOR SITE ACTIVITIES:
- Masonry work on the exterior façade will continue.
- Washing activities will take place on the south and west elevations of Westmorly Hall.
- Scaffolding installation will continue along North & West elevations of the Library.
- Man/material hoist will be operating while the site is open.
- On weekdays the lift will operate 7am-5pm and Saturday it will operate from 9am-4:30pm.
- Dewatering equipment set up will continue at Russell Hall.
- There will be a boom truck in the back parking lot placing steel throughout the week.
INTERIOR ACTIVITIES:
- Interior rough carpentry will continue.
- Interior demolition of Westmorly and Russell Halls.
- Steel erection within Westmorly Hall will continue.
- Saw cutting and removal of Russell Hall slab will continue.
WORK HOURS:
- Monday to Friday: 7am to 3:30pm
- Saturday 11/25 – 9am to 4:30pm