The following summarizes the work planned on the Adams House Phase 3 renovation for the week of January 29th. Please note that items in BOLD are expected to generate some noticeable noise.
PUBLIC WAY IMPACTS:
- Continuous deliveries and dumpster swaps throughout the week.
- Crews will be live loading demo debris from the back parking lot to a dumpster staged on Bow Street.
- Trucking of soils and concrete will continue next week from Bow Street Gate 2.
- Ongoing deliveries will occur, and concrete pump truck will be within the site fence.
- Eversource will be working at the intersection of Bow Street and Arrow Street.
EXTERIOR SITE ACTIVITIES:
- Masonry work on the exterior façade will continue.
- Cutting along the North, West and South elevations of the Library Commons and washing on South/East elevation of Westmorly Hall.
- Scaffolding installation will continue on the South elevation of Russell Hall and North elevation of Westmorly Hall.
- A roofing contractor will be mobilizing early next week for Russell Hall slate demolition and abatement.
- Man/material hoist will be operating while the site is open.
- On weekdays the lift will operate 7:00am-3:30pm and Monday/Saturday it will be in operation from 9:00am-4:30pm.
INTERIOR ACTIVITIES:
- Interior wood framing will continue in Westmorly Hall.
- Interior demolition of concrete in Russell Hall.
- Demolition of Westmorly Hall ground level slab is scheduled for the end of the week.
- Drywall ignition barrier will continue on the 3rd & 4th floor of Westmorly Hall.
- Excavations within Russell Hall basement will continue.
- Excavations for under slab utilities within Westmorly Hall will continue.
- Rebar & concrete work is ongoing.
WORK HOURS:
- Monday to Friday: 7:00am to 3:30pm
- Saturday 2/3 – 9:00am to 4:30pm