Month: January 2024

Week of January 29, 2024

The Western Avenue utility crossing roadway work is finalized and is extending onto Kresge Way. This work will finish this winter and is being coordinated with University operations.   Kresge Way Temporary RelocationAs part of Harvard’s infrastructure improvements in Allston, the University has extended thermal piping and electrical/telecommunications duct banks from the District Energy Facility across Western Avenue to Kresge Way, the…Continue Reading Week of January 29, 2024

Week of January 22, 2024

175 North Harvard Street Project Construction Impacts Update • Project enabling activities are progressing through January in preparation for building construction. o Bulk excavation continues with soil removal and the hauling of soil off site taking place for the next few weeks. o Periodic steel deliveries continue. o Truck traffic in and out of the…Continue Reading Week of January 22, 2024

Week of January 15, 2024

175 North Harvard Street Project Construction Impacts Update • The job site will be open and active on Monday, January 15. • A small crew being present on site tomorrow, Saturday, January 13, performing some low impact work to dewater the site following the impending heavy rain. • Project enabling activities continue through January in…Continue Reading Week of January 15, 2024

Week of January 22, 2024

The Western Avenue utility crossing roadway work is finalized and is extending onto Kresge Way. This work will finish this winter and is being coordinated with University operations.   Kresge Way Temporary RelocationAs part of Harvard’s infrastructure improvements in Allston, the University has extended thermal piping and electrical/telecommunications duct banks from the District Energy Facility across Western Avenue to Kresge Way, the…Continue Reading Week of January 22, 2024

Week of January 15, 2024

The Western Avenue utility crossing roadway work is finalized and is extending onto Kresge Way. This work will continue this month and is being coordinated with University operations.   Kresge Way Temporary RelocationAs part of Harvard’s infrastructure improvements in Allston, the University has extended thermal piping and electrical/telecommunications duct banks from the District Energy Facility across Western Avenue to Kresge Way, the…Continue Reading Week of January 15, 2024

Week of January 8, 2024

After hours snow removal work will take place through the winter months as inclement weather events occur.  The Western Avenue utility crossing roadway work is finalized and is extending onto Kresge Way. This work will continue this month and is being coordinated with University operations.   Kresge Way Temporary Relocation As part of Harvard’s infrastructure improvements in Allston, the…Continue Reading Week of January 8, 2024

Week of January 8, 2024

175 North Harvard Street Project Construction Impacts Update • The job site will be active on Monday, January 15. • Project enabling activities continue through January in preparation for building construction. o Building demolition activities are complete. o Soil excavation and hauling soil away from the site are ongoing for the next few weeks. o…Continue Reading Week of January 8, 2024