Week of January 29, 2024

The following summarizes the work planned on the Adams House Phase 3 renovation for the week of January 29th. Please note that items in BOLD are expected to generate some noticeable noise.
 
PUBLIC WAY IMPACTS:

  • Continuous deliveries and dumpster swaps throughout the week.
  • Crews will be live loading demo debris from the back parking lot to a dumpster staged on Bow Street.
  • Trucking of soils and concrete will continue next week from Bow Street Gate 2.
  • Ongoing deliveries will occur, and concrete pump truck will be within the site fence.
  • Eversource will be working at the intersection of Bow Street and Arrow Street.

EXTERIOR SITE ACTIVITIES:

  • Masonry work on the exterior façade will continue.
    • Cutting along the North, West and South elevations of the Library Commons and washing on South/East elevation of Westmorly Hall.
  • Scaffolding installation will continue on the South elevation of Russell Hall and North elevation of Westmorly Hall.
  • A roofing contractor will be mobilizing early next week for Russell Hall slate demolition and abatement.
  • Man/material hoist will be operating while the site is open.
    • On weekdays the lift will operate 7:00am-3:30pm and Monday/Saturday it will be in operation from 9:00am-4:30pm.

INTERIOR ACTIVITIES:

  • Interior wood framing will continue in Westmorly Hall.
  • Interior demolition of concrete in Russell Hall.
  • Demolition of Westmorly Hall ground level slab is scheduled for the end of the week.
  • Drywall ignition barrier will continue on the 3rd & 4th floor of Westmorly Hall.
  • Excavations within Russell Hall basement will continue.
  • Excavations for under slab utilities within Westmorly Hall will continue.
  • Rebar & concrete work is ongoing.

WORK HOURS:

  • Monday to Friday: 7:00am to 3:30pm
  • Saturday 2/3 – 9:00am to 4:30pm