Week of January 22, 2024

The following summarizes the work planned on the Adams House Phase 3 renovation for the week of January 22nd. Please note that items in BOLD are expected to generate some noticeable noise.
 
PUBLIC WAY IMPACTS:

  • Continuous deliveries and dumpster swaps throughout the week.
  • Crews will be live loading demo debris from the back parking lot to a dumpster staged on Bow Street.
  • Trucking of soils and concrete will continue next week from Gate 2 off of Bow Street.

EXTERIOR SITE ACTIVITIES:

  • Masonry work on the exterior façade will continue.
    • Cutting along the north, west and south elevations of the Library Commons and washing on south/east elevation of Westmorly Hall.
  • Scaffolding installation will continue on the south elevation of Russell Hall and north elevation of Westmorly Hall.
  • Crane for temporary steel at back parking lot is tentatively scheduled for Monday-Wednesday next week.
  • Man/material hoist will be operating while the site is open.
    • On weekdays the lift will operate 7:00am-3:30pm and Saturday it will be in operation from 9:00am-4:30pm.

INTERIOR ACTIVITIES:

  • Interior wood framing will continue in Westmorly Hall.
  • Interior demolition of concrete in Russell Hall.
  • Demolition of Westmorly North Level 1 is scheduled for end of the week.
  • Abatement will continue within the project at the Library and Dining Hall.
  • Drywall ignition barrier installation will continue on the 3rd &  4th floor of Westmorly Hall.
  • Excavations within Russell Hall basement will continue.
  • Excavations for under slab utilities within Westmorly Hall will continue.
  • Rebar & concrete work is scheduled to begin Monday in Russell Hall basement & Westmorly hall ground level.  

WORK HOURS:

  • Monday to Friday: 7:00am to 3:30pm
  • Saturday 1/27 – 9:00am to 4:30pm