Day: June 14, 2024

Week of June 17, 2024

Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank Enterprise Research Campus (ERC) 92 Seattle Street 175 North Harvard Street,100 South Campus Drive, 201 Western Avenue Lot Expansion Construction has begun on the new American Repertory Theater (ART), which will be located at the front of the 175 North Harvard parcel with the new Harvard…Continue Reading Week of June 17, 2024