Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank Enterprise Research Campus (ERC) Residential/Hotel Laboratory and Office Buildings Greenway Treehouse Conference Center Waterline Installation on Western Avenue Building Mock-Ups Eversource Conduit Project Milestone Thermals General North Allston Storm Drain Extension Project (NASDEP) The NASDEP, a project designed for Boston Water and Sewer Commission…Continue Reading Week of September 16, 2024
Week of September 16, 2024
175 North Harvard Street Project Construction Impacts Update The following is an overview of the work taking place at the 175 North Harvard construction site at thefuture location of the new Harvard University affiliate housing building and American Repertory Theatre(ART):…Continue Reading Week of September 16, 2024